1.
PURPOSE
1.1.
The
purpose of this document is to explain the methods used for Tower Erection works.
2.
SCOPE
2.1.
This
procedure applies to all personnel who are involved in and are responsible for
the execution of Tower Erection works.
3.
DEFINITION
3.1.
Nil.
4.
REFERENCE
4.1.
Technical
Specification and Contract Agreement of 500 KV Transmission Line jawa 1 CCP project.
5.
SAFETY
5.1.
All
work will be carried out in accordance with the WTE Health, Safety and Environment
procedure.
5.2.
The
following Personel Protective Equipment (PPE) must be provided :
· Hard Hat (Safety Helm)
· Gloves
· Safety Belts double lanyards type.
5.3.
Climbing
Unattached
movement is NOT permissible. Access up and down the climbing leg / stepbolts is
carried out using double lanyards or a fall rope and slide chuck mechanism
(cobra). When traversing across a tower to a work position, it is an essential
requirement that the climbers must be securely attached to a safe anchorage at
all times.
5.4.
Working
It is an
essential requirement that when at the work point, the person is in a secure
position attached to a safe anchorage at alltimes.
5.5.
Climbing
Belt and Lanyards
All
climbers must use a climbing belt with two lanyards. Belt and lanyards should
be checked daily for obvious damage, broken stitches cuts or wear. Checking on
safety hooks and buckles should also be carried out daily.
5.6.
All
workers have a responsibility to work safety according to the Company
Guidelines. lnparticular they must :
Ø Wear the safety equipment provided.
Ø Check that the lower earthing is
connected.
Ø Check their equipment daily and request the
replacement of faulty items.
Ø Climb down from the tower during rain.
Ø Never erect the tower if the foundation is
not backfilled.
Ø Not work at night unless special
provisions have been made.
Ø All Lifting Hooks must have an approved
safety catch.
Ø All type of steel wire rope and nylon rope
must be tension tested before use.
Ø At every 3 towers erection, bamboo derrick
must be checked against crack and rope lightening.
Ø Anchorage must use anchor drill or other
strong tools.
Ø lf you are not sure about the anchor drill
(example : rock area), please install the- spare anchor drill (2 pieces) at
back.
Ø lvlaximum lifting capacity for bamboo
derrick is 400 Kg.
Ø Maximum lifting capacity for 70 ft aluminium
denick is 1.000 Kg.
Ø Maximum lifting capacity for modified 25m
Tesmec aluminium derrick model number FAL 320 is 1000 Kg.
Ø Maximum lifting capacity for WTE 21m
lattice steel derrick is 1.000 Kg.
5.7.
ln
the event that a winch bond becomes snagged on the tower, the lift should be
stopped and the tension reduced on the bond before releasing the snagged
portion of the bond.
5.8.
The
foreman an is responsible for implementing this erection safety procedure. ln addition,
a person should be appointed "banksman" to observe and direct the
lifting operations involving the winches.
6.
MATERIALS
6.1.
The
following materials are required for Tower Erection :
Ø Angle Steel work.
Ø Plates.
Ø Nuts, Bolts and Washers.
Ø Anti Climbing Devices.
6.2.
All
materials are hot dip galvanized and care must be taken to avoid damaging,
scratching or marking this protective coating. Any defect in the galvanizing
should be reported immediately.
6.3.
All
materials are issued to site from the store. The procedure for storage,
batching and issue of tower materials to site is described in the Work
lnstruction for store.
6.4.
All
materials should be checked for compliance with the specification before
leaving the store.
6.5.
MATERIAL
TRANSPORTATION
6.5..1. Material is transferred from the site
store to the tower location by using truck or any othersuitable means. Smaller
truck may be used, for example, where road access is very narrow.
6.5..2. lf there is no access road access, the
steelwork should be carried from the nearest roadside point to tower location by
hand carry.
6.5..3. The materials unloaded at the tower site
must be stacked on timber batons, for ease of lifting and to keep the steelwork
clean (any dirt must be washed / brushed off).
6.5..4. The steelwork should be laid out in the
sequence it is required for tower erection.
6.5..5. Special care must be taken to avoid
damaging the steelwork in any way. Scratches can berepaired using 'Cold
calvanizing Paint' as approved bythe Engineer. Steelwork with major damage must
be replaced.
7.
PREPARATION
FOR TOWER ERECTION
7.1.
The
tower foundation must be back filled before starting any tower erection.
7.2.
The
foundation concrete must have reached a strength of specification.
7.3.
The
surveyor must check the following stub dimensions :
Ø Back to back (face and diagonal).
Ø Relative levels of top of stubs.
Ø Slope of stubs.
As shown in work sheet for foundation work.
7.4.
The
tower earthing must be installed according the drawings. Make sure that tower
earthing has been installed before erection and has to be measured after
erection finished.
7.5.
Assembly
of steelwork on the ground should be carried out in dedicated areas to avoid
people working overhead.
7.6.
Good
housekeeping (i.e. keeping the site tidy) should be maintained during the tower
erection operation.
8.
PROCEDURE
FOR ERECTION OF AA TOWER
8.1.
The
main equipment and plant required are :
Ø Winch and Bond.
Ø Derrick
Ø Spanners.
Ø Derrick guys.
Ø Stakes.
Ø Snatch blocks.
Ø Nylon rope.
Ø Pullifts.
Ø Lifting hooks complete with safety catch.
8.2.
The derrick is manually handled into resting position
on the chimney of one leg. Head guys and winch bonds are fitted as shown on the
sketch below :
8.3.
The
head guys must be secured to a ground anchor such as Molex Anchors or concrete
blocks at a safe distance from the derrick. The foreman must select appropriate
locationsand check they are correctly installed. lt is not acceptable to use
trees of any type for ground anchors.
8.4.
The
winch must be anchored to the ground using either stakes, molex anchors.
8.5.
LEG
EXTENSIONS
8.5..1. The first lift is the main leg which fits
immediately above the stub. After lifting into position and bolting up the
splice plates and bosom angles, a holding out rope is fixed to the top of the
main leg to maintain the correct slope.
8.5..2. The derrick is then moved to the next leg
and the operation described in 8.5.1 is repeated.
8.5..3. The horizontal and bracing bars, that fit
between these legs are then lifted into position.
8.5..4. The derrick is moved on to the remaining
legs, in turn and operations 8.5.1 & 8.5.3 are repeated until all 4 leg
extensions are in place with all the horizontal and bracing members.
8.6.
BODY
EXTENSIONS
8.6..1. The bamboo derrick is then lifted to the
first horizontal at one of the main legs. The winch bond passes through a
snatch block at the bottom of the main leg used by the derrick and through a
second snatch block at the top of the derrick.
8.6..2. The same procedure as described in 8.5.1
to 8.5.4 is followed to compiete the bodyextension.
8.6..3. Providing the derrick is 14m long it may
be possible to lift the two adjacent main legs into position by leaning the
derrick towards each leg by adjusting the derrick head guys. Head and foot
holding out ropes are attached to each main leg to manuver them into position. ln
this way the derrick will only be moved to one other leg. However, the derrick
must not normally lean more than 15" to the vertical.
8.7.
COMMON
PORTION
8.7..1. The derrick is lifted, as required, to
each new level of the tower.
8.7..2. All material can be lifted into position
by the derrick fixed at one leg. The derrick is leaned over, as required, by
adjusting the derrick head guys.
8.8.
CROSSARMS
8.8..1. The cross arms are lifted into place when
the common portion body is complete.
8.8..2. The earth wire cross arms are lifted
first.
8.8..3. The top, middle and bottom cross arms are lifted
in two sections (an outer and an inner section). The outer section is lifted
into position with the winch bond passing through a snatch block on the earth
wire cross arms take off plate.
9.
PROCEDURE
FOR ERECTION OF ANGLE (DD / DDR / EE} TOWERS
9.1.
The main equipment and plant
required are :
·
2.5T winch (Capstan Winch) and bond.
·
Type of derrick : 70'Aluminium
derrick or Modified 25m, Tesmec Aluminium derrick model number FAL 320 or WTE 21m
lattice Steel derrick.
·
1.5T Tirfors.
·
1.5T Pull Lifts.
·
Head guys.
·
Wallace toggles.
·
3m and 4m . 12mm Wire rope slings.
·
1.5m x 16mm Wire rope slings.
·
1T & 1.5T SWL D Shackles.
·
Anchor drill.
·
Snatch blocks.
·
Nylon rope
9.2.
The
procedure for lifting the steel work into position is the same as for described
in section 8. however, since the tower material is heavier and the base size of
angle towers is wider, a larger aluminium derrick is used. The 'floating
derrick' methods is used with guys connected to the main legs of the towers.
9.3.
The
following safety considerations should be considered at all times.
·
The
derrick should be lifted into the wind.
·
The
derrick should not be used at an angle > 30˚ to the vertical.
·
Lifting
hooks shall be completed with safety catch.
9.4.
The
following operations 9.5 and 9.6 describe the additional information required
ti lift lhe derrick into position and subsequently raise the derrick to new
levels of the tower.
9.5.
RAISING
DERRICK TO THE VERTICAL POSITION
9.5..1. This is a straight forward operation,
which requires good co-ordination to avoid accidents. Lt is important that the
Senior Erection Supervisor attends every lifting operation.
9.5..2. The derrick is laid out and assembled with
its foot on a base plate at the centre of the tower. Slings are used to anchor
lhe base plate to the existing stubs.
9.5..3. The winch is positioned by the supervisor
to suite the site conditions. lt is important that the winch operator has good
visibility to all lifting operations.
9.5..4. While the derrick is lying on the ground,
four guys are pulled out from the head of the derrick. They are positioned at
90˚ to each other and anchored at a distance equal to the height of the
derrick.
Item
|
Description
|
Qty
|
Item
|
Description
|
|
Qty
|
1
|
Aluminium derrick 70 Feet or WTE 21m lattice steel
derrick
|
1
|
7
|
Erectionn Winch bond dia. 12mm with length 250m
|
|
1
|
2
|
77m , 8 ,12mm wire rope guys
|
4
|
8
|
4m * 12mm wire rope sling
|
|
2
|
3
|
3m * 12mm wire rope sling
|
4
|
9
|
1T SWL "D' Shackles
|
|
4
|
4
|
2.5T SWL Erection Winch
|
1
|
10
|
Tirfor 1.5T
|
|
4
|
5
|
A-Frame for erection bond
|
1
|
11
|
1.5m * 16mm wire rope slings
|
|
4
|
6
|
Anchor drill
|
15
|
12
|
1.5T SWL "D' Shackles
|
|
18
|
9.5..5. A falling derrick is then positioned over
the base plate. This is typically an a frame made up from two main legs. lt is
common practice to connect a sling from the a frame to the derrick to control
its fall once the derrick rises above the top of a frame.
9.5..6. The winch bond is passed through the head
of the a frame and head to the derrick and caught off at the base plate.
9.5..7. The derrick is now ready for lifting.
Before this operation begins the senior supervisor will check :
· All the guys are correctly positioned with
men at each anchor position.
· The bonds and guys are not obstructed.
9.5..8. The derrick is slowly raised by the winch.
The side guys should be monitored to ensure that the derrick rises in line with
the winch.
9.5..9. When the derdck is above 45˚ the
rear guy should be very closely monitored. lt need to be applied quickly if
there is a danger of the derrick falling over towards the winch but otherwise
should have some slack to that it does not work against the winch.
9.5..10. After the derrick has reached the vertical
position all four guys are caught off and the derrick is ready to begin lifting
operation.
Item
|
Description
|
Qty
|
Item
|
Description
|
Qty
|
1
|
Aluminium derrick 70 Feet or WTE 21m lattice steel
derrick
|
1
|
7
|
Erectionn Winch bond dia. 12mm with length 250m
|
1
|
2
|
77m , 8 ,12mm wire rope guys
|
4
|
8
|
4m * 12mm wire rope sling
|
2
|
3
|
3m * 12mm wire rope sling
|
4
|
9
|
1T SWL "D' Shackles
|
4
|
4
|
2.5T SWL Erection Winch
|
1
|
10
|
Tirfor 3.5T
|
4
|
5
|
A-Frame for erection bond
|
1
|
11
|
1.5m * 16mm wire rope slings
|
4
|
6
|
Anchor drill
|
15
|
12
|
2.5T SWL "D' Shackles
|
18
|
9.6.
RISING
DERRICK TO HIGHER LEVEL
9.6..1. When the derrick is lifted off the base
plate it becomes a “floating” derricks. It is supported from pennants connected
to all four tower legs. The head guys pass through the blocks at the top of the
main legs and continue to the stubs where they can be adjusted by tirfors.
9.6..2. Position on the main legs is chosen to fix
the pennants. This is chosen to ensure :
· One - third of the derrick remains inside
the erected tower.
· The pennants hang at an angle of < 30˚ to
the derrick.
9.6..3. The derrick is lifted using a "Lazy"
bond connected from the winch through a block at the top of one main leg and on
to the bottom of the derrick.
9.6..4. The head guys are released as the derrick
is lifted. When the derrick has been raised to the correct height the pennants
are connected and the head guys caught off.
9.6..5. The derrick is then ready to re-start
lifting operation.
10.
TOWER
CHECKING
10.1. After completion of the tower erection all
bolts must be checked tightness, This operation should follow a logical
sequence from bottom to top of the tower to ensure all bolts are checked.
10.2. The supervisor should complete and sign
the Post Erection Inspection Form.
11.
EXCEPTION
11.1. ln the steep area or narrow area, to pull
the derrick can use the kick back system (Different with the normal procedure
on Point 9.5)
12.
RECORD
12.1. Post Erection lnspection.
12.2. Certificate of Tower Earlhing
13.
APPENDIX
13.1. Work Flow for Tower Erection.
13.2. Post Erection Inspection Form.
|
No comments:
Post a Comment